The crane has scientific layout and beautiful appearance. The operator’s room is side independently on one side, with good vision field, it creates a good work environment for the operator. The crane is convenient to operate and easy to maintain and repair. It is an ideal construction machine for construction enterprises. The machine has four kinds of work structures: Lifting, circumgyrating, variable ranges, and top lifting. The four structures can work in combination as well as independently so as to improve work efficiency. The top lifting structure is used to increase the height of the tower or lower the tower. The lifting control of this machine has three choices: Frequency conversion stepless speed adjusting, double speed wire winding motor speed adjusting, and tri-speed motor speed adjusting. The circumgyrating control has two options: Frequency conversion stepless speed adjusting and wire winding motor speed adjusting. The range adjustment control has two selections: Frequency conversion stepless speed adjusting and tri-speed motor speed adjusting. The above settings can be made according to the demands of the customers. All the models work stably and can fully satisfy different needs. The lifting arm can rotate 540 to the left and right. The circumgyrating and range adjusting are agile and reliable, and the hoisting positioning is accurate. Thus the crane can satisfy the need for vertical and horizontal transportation in construction operation.
2 Times Multiplying (2 falls) magnification
Jib length (m) |
3-21.4 |
22 |
23 |
24 |
25 |
26 |
27 |
28 |
29 |
30 |
Load (t) |
2 |
1.94 |
1.85 |
1.77 |
1.69 |
1.62 |
1.56 |
1.50 |
1.45 |
1.39 |
Jib length (m) |
31 |
32 |
33 |
34 |
35 |
36 |
37 |
38 |
39 |
40 |
Load (t) |
1.35 |
1.30 |
1.26 |
1.22 |
1.18 |
1.14 |
1.11 |
1.08 |
1.05 |
1.02 |
Jib length (m) |
41 |
42 |
43 |
44 |
45 |
46 |
47 |
48 |
49 |
50 |
Load (t) |
0.99 |
0.97 |
0.94 |
0.92 |
0.89 |
0.87 |
0.85 |
0.83 |
0.81 |
0.80 |
|
|
|
|
|
|
|
|
|
|
|
|
4 Times Multiplying
Jib length (m) |
3-10.966 |
11 |
12 |
13 |
14 |
15 |
16 |
17 |
18 |
19 |
20 |
Load (t) |
4 |
3.98 |
3.64 |
3.36 |
3.10 |
2.89 |
2.70 |
2.54 |
2.39 |
2.26 |
2.14 |
Jib length (m) |
21 |
22 |
23 |
24 |
25 |
26 |
27 |
28 |
29 |
30 |
31 |
Load (t) |
2.04 |
1.94 |
1.85 |
1.77 |
1.69 |
1.62 |
1.56 |
1.50 |
1.45 |
1.39 |
1.35 |
Jib length (m) |
32 |
33 |
34 |
35 |
36 |
37 |
38 |
39 |
40 |
41 |
42 |
Load (t) |
1.30 |
1.26 |
1.22 |
1.18 |
1.14 |
1.11 |
1.08 |
1.05 |
1.02 |
0.99 |
0.97 |
Jib length (m) |
43 |
44 |
45 |
46 |
47 |
48 |
49 |
50 |
|
|
|
Load (t) |
0.94 |
0.92 |
0.89 |
0.87 |
0.85 |
0.83 |
0.81 |
0.80 |
|
|
|
Basic Parameter:
Hoisting
Mechanism |
Motor |
Model |
|
YZD200L1-4/8/24 |
Power |
kW |
15 |
13 |
3.5 |
Reducer |
Total Drive Ratio |
i |
12.64 |
Drum |
Rope Capacity |
m |
280 |
Brake |
Model |
|
YWZ-250-40 |
Brake Moment of Force |
N·m |
600 |
Wire steel Rope |
Rope Max. Attraction |
N |
16500 |
Specification |
|
6×37-11-1770-Ⅰ |
Lifting Speed |
2 Time Multiplying Power |
m/min |
62 |
31 |
7.7 |
4 Time Multiplying Power |
31 |
15 |
3.8 |
Slewing(swing) Mechanism
|
Motor |
Model |
|
YZR132M-6 |
Power |
kW |
3.7 |
Reducer |
Model |
|
XX4-100.180 |
Drive Ratio |
i |
180 |
Coupler |
Model |
|
YOX.280 |
Rotating Speed |
|
r/min |
0.6 |
Trolleying Mechanism |
Motor |
Model |
YEZS112M-4/6 |
Power |
kW |
2.2 |
1.5 |
Reducer |
Type |
|
Grade One |
Drive Ratio |
|
38 |
Wire steel Rope |
Specification |
6×19-6.2-1770-1 |
Rope Max. Attraction |
N |
5600 |
Trolleying speed |
|
m/min |
22/33 |
Hydraulic Jacking Mechanism |
Hydraulic pump station |
Model |
|
YQY Series |
Working Pressure |
MPa |
20 |
Oil Cylinder |
Model |
|
20.5 |
Jacking Speed |
m/min |
0.4 |
Max. jacking Force |
t |
50 |
Motor |
Model |
|
Y132M-4 |
Power |
KW |
5.5 |
Jacking Speed |
r/min |
1440 |
|
|
|
|
|
|
|
|